B BROCENT

Managed IT Services Lesson: Our Cross-Border IT Infrastructure Deployment Succeeded, Yet We Paid in Full Over One Customs Document

Our cross-border IT infrastructure deployment and onsite install succeeded, but unclear customs terms in this IT outsourcing deal meant a RMB 300,000+ payout

IT engineer configuring network cables in a server rack during an onsite IT infrastructure deployment
The short version: As a managed IT services and IT outsourcing provider, we completed a cross-border IT infrastructure deployment for a domestic equipment manufacturer: the equipment reached the overseas data centre on schedule, our onsite engineers finished all rack installation and commissioning, the client confirmed in writing, the overseas buyer accepted the equipment and paid, and the court upheld all of our service fees. But because our third-party freight forwarder used consolidated customs declaration, the client could not obtain an export declaration naming itself as the shipper, could not complete foreign exchange settlement, and the payment was returned. The court found that we, as the entrusted party, were at fault, ordered us to pay the full payment amount plus interest, and the appeal court upheld the ruling. We have paid in full. This report explains the court's reasoning, the laws behind it, where we went wrong, and how clients and peers can avoid the same outcome.

Why Publish a Lost Lawsuit?

Few IT outsourcing providers talk publicly about cases they have lost. Rarer still: in this case the IT service we delivered was itself a success, and what we lost on was a document outside the boundary of that service. We decided to write it up for three reasons.

  • The outcome is final. The judgment has taken effect and the compensation has been paid in full. This article is not an argument, and it does not re-evaluate the court's findings.
  • This risk is common across the industry. Many IT service providers casually take on "non-core" tasks for clients: procurement on their behalf, shipping, customs declaration, payments. Done well, it is added value. When it goes wrong, the provider carries the full loss.
  • Clients also need to know how to state their requirements. In this case, what the client actually needed was never written down from contract signing through delivery, and the court ended up answering the question "what was actually agreed?"

The client's name, the overseas buyer, the case number, the court, individual names and exact amounts have been anonymised. Every description of the ruling follows the facts and reasoning set out in the final judgment.

What Happened: How Did a Service Contract Worth Under RMB 60,000 Become a Liability of Over RMB 300,000?

What the contract said

In spring 2022, a domestic network equipment manufacturer (the "Client") signed a purchase order with a company in Singapore for equipment worth approximately US$41,000. To fulfil the order, the Client signed a Network Equipment Installation and Deployment Agreement with us. It had two parts:

  • Service 1: Ship a batch of network switches from Chengdu, China to a designated data centre in Singapore, "including logistics and customs clearance, by air freight," door to door.
  • Service 2: On-site rack installation, setup and commissioning labour.

In the quotation email sent before signing, we stated that the freight "includes duties and double clearance, door to door." "Double clearance" means that customs clearance at both the exporting and importing ends is handled by the logistics provider.

The contract also contained a clause that later became critical: the Client was entitled to require the supplier to provide "a proof of receipt acknowledged by the Client or end user, sufficient for the Client's payment collection"; and if the services did not meet the requirements of the Client or end user, the Client could defer payment of the corresponding service fees.

How performance went

  • We arranged for a third-party freight forwarder to collect the goods. The goods were trucked from Chengdu to Shenzhen, cleared export customs at the Shenzhen port, were flown to Singapore, and arrived on schedule.
  • The Client changed the delivery address and date twice, and we accommodated both changes.
  • Our engineers completed all rack installation, setup and commissioning on site. Actual working hours were twice the original estimate. We reported the additional charges by email, and the Client replied the same day: "OK, no problem."
  • About a week after delivery, the Client's project staff asked in an instant messaging chat whether we could provide the export customs declaration, noting that international settlement is based on it and that it is "a must." Our logistics colleague replied: "I'll ask the logistics side. I used a freight forwarder for shipping."

This is where the problem lay. The third-party forwarder had used a common "door-to-door, duties-included, double clearance (DDP-style consolidated shipping)" arrangement: goods from multiple shippers are combined under a single customs declaration, loaded into the same air cargo container on one master air waybill, and split up for delivery at the destination. Under this method, there is no separate export declaration naming the Client as the shipper, and no air waybill naming the Client as the consignor.

How the money "disappeared"

About five months after delivery, the overseas buyer remitted roughly US$41,000 to the Client. Under foreign exchange administration requirements, the Client had to prove the transaction was genuine in order to receive and settle the foreign-currency export proceeds, and the core document proving "this shipment was exported by me" is the customs declaration. The Client could not obtain one, and within about ten days the money was returned to the overseas buyer.

The Client then stopped paying our remaining service fees and notified us in writing that we must bear the loss.

The litigation result

  • The Client sued: It demanded that we hand over the customs declaration and the air waybill, or, failing that, pay the full payment amount (approximately RMB 300,000 at the exchange rate on the day) plus interest.
  • We counterclaimed: We sought the remaining service fees and the additional charges, about RMB 50,000 in total, plus interest on late payment.
  • First-instance judgment: We were ordered to pay the full payment amount, plus interest at the one-year Loan Prime Rate (LPR, China's benchmark lending rate) on the amount from the day after the collection failed. The Client was ordered to pay us the remaining service fees and additional charges. Our claim for interest on late payment was dismissed.
  • Appeal: The original judgment was upheld.
  • Performance: After the two sides' mutual monetary debts were set off, we paid the Client the balance. The compensation has been fully paid.

Here is the arithmetic. The total service fees under this contract were under RMB 60,000. The principal and interest we ultimately bore came to over RMB 300,000, about five times the total contract value. That excludes court fees at two instances, legal fees and the time our team invested.

What Did the IT Service Itself Achieve? A Successfully Delivered Cross-Border IT Infrastructure Deployment

Before discussing where we lost, let us be clear about what went right. This is not meant to reduce our responsibility. It determines the nature of the case: the court did not find any problem with the quality of our IT service. The dispute centred on a customs document outside the service boundary.

Cross-border logistics and onsite deployment completed smoothly

  • The goods arrived on schedule. The equipment was collected in Chengdu, cleared export customs in Shenzhen, was flown to Singapore, and arrived within the door-to-door timeframe set in the contract.
  • Both ad hoc changes were absorbed. Because of changing data centre conditions, the end user changed the delivery address and rack-in date twice, and finally asked for delivery over two days, with the equipment not yet racked unpacked into storage. We rebooked the unloading bay and reworked the onsite schedule to the new requirements.
  • Onsite IT support was completed in one go. Our onsite engineers completed rack installation, setup and commissioning of the whole batch of switches. Actual effort was 6 person-days, double the 3 originally planned. The onsite team absorbed the extra workload, and the whole batch was online within a week.

Both the client and the court confirmed the results

  • Written confirmation from the client. After completion we sent the work dates and schedule, and the client's project staff confirmed by email the same day.
  • The end user accepted, used and paid. The overseas buyer signed for the equipment, put it into use, and remitted the full payment to the client.
  • The court upheld all of our service fees. The judgment held that our remaining service fees and the additional charges must be paid, with the additional charges based on the very email in which both sides confirmed the actual working hours.

This is Brocent's core work as an IT outsourcing provider: multi-country IT support coverage, onsite engineer dispatch, and IT infrastructure deployment done at the end user's pace. It was done. What we lost on was an errand that is not part of core IT service but was written into the same contract. That is exactly what this article wants to warn peers and clients about.

How Did the Court Decide? Three Pillars of the Judgment

Understanding the logic matters more than remembering the result. The court's reasoning breaks down into three steps.

Step 1: "Logistics + customs clearance" in an IT service contract was treated as a freight forwarding contract

Although the contract was titled an "installation and deployment agreement," the court held that, for the logistics and customs clearance services the Client entrusted to us, the parties had formed a freight forwarding contract relationship, to which the rules on entrustment contracts apply.

This step determined the standard of liability. Article 929, paragraph 1 of the Civil Code of the PRC provides: "Where a paid entrustment contract causes loss to the principal through the fault of the agent, the principal may claim damages."

Note the threshold: a paid entrustment requires only "fault," not "intent or gross negligence." We were paid a service fee, so we were a paid agent, and the standard is ordinary fault.

Step 2: Consolidated declaration made "the declaring entity inconsistent with the real trading party"

The court held that the contract required us to provide clearance services and "proof of receipt sufficient for the Client's payment collection." The third-party forwarder did not file a separate declaration for the Client's goods but combined them with other shipments under one declaration, which meant:

  • The shipper on the customs declaration was not the real exporter. The court cited Article 24 of the Customs Law: the consignee of imported goods and the shipper of exported goods must declare truthfully to Customs.
  • The Client could not properly receive and settle the foreign-currency proceeds. The court also cited Article 12 of the Regulations on Foreign Exchange Administration: current-account foreign exchange receipts and payments must rest on a genuine and lawful transaction, and financial institutions must reasonably review the authenticity of transaction documents and their consistency with the foreign exchange receipts and payments.

The court also stressed that there was no evidence that the parties had agreed to this method of declaration, and before the declaration we had not clearly told the Client about it.

Step 3: With professional qualifications, you are expected to "know"

This is the point that should alarm us most.

In the proceedings we argued that if the Client wanted to declare in its own name, it should have issued an agency customs declaration authorisation and completed the corresponding steps on the electronic port platform, and that the Client never did so. The court's response was that we, as the provider of the clearance service, had never asked the Client for these formalities.

The court also noted that our business scope included import and export of goods and agency import and export, and that we held a customs registration as a consignee and consignor of imported and exported goods. It therefore found that we knew the Client, as an exporter, needed to receive and settle foreign-currency proceeds, and ought to have known that consolidated declaration could prevent the Client from doing so. Because we used it anyway, we were at fault.

In other words: the more complete your qualifications, the higher the court's expectation of what you "should have known." An extra line in your business licence or an extra registration can become, in litigation, the basis for saying "you ought to have understood."

The counterclaim: the fees were awarded, the interest was not

The court upheld our claim for the remaining service fees, including the additional charges the Client disputed in the proceedings. The reason was that the emails showed the Client's project staff had replied "OK" the same day to the actual working hours and the additional charges, so the court allowed the fees according to the pricing method in the contract.

But our claim for interest on late payment was dismissed. The court held that, since we were at fault in performing the entrusted task and the Client still could not recover its payment, the Client's refusal to pay was a lawful defence against performance.

This is also worth remembering: one email replied to on the same day helped us secure roughly RMB 20,000 in additional charges, while a customs declaration request that was never handled in writing cost us all the interest and left us with liability several times the contract value.

What Is the Real Problem? It Is Not "One Customs Declaration"

If we read this only as "we forgot to get a customs declaration," we would miss the real lesson. After repeated discussion, we think it comes down to three things.

1. We were selling not just a "result" but also "compliance documentation"

In our view, the result of Service 1 was "goods delivered safely, clearance completed." That result was indeed achieved: the goods arrived, the equipment was installed, and the buyer paid.

But from the Client's perspective, a cross-border delivery has three lines: the flow of goods, the flow of funds and the flow of documents. Arrival of the goods completes only the first. Whether the money can be received depends on the third. Foreign exchange supervision checks that the "three flows" are consistent, and what connects them is precisely that customs declaration naming the Client as shipper.

For a service provider, whenever the client will use the result of the service for a further compliance step, such as receiving foreign exchange, claiming a tax refund, audit, an insurance claim or booking an asset, the documents themselves are part of the deliverable. It is not enough to deliver "the job got done."

2. Risk travelled from the Client's downstream contract to the service provider

We were not a party to the Client's sales contract with the overseas buyer, its payment terms or its settlement arrangements. In the proceedings we also argued that the buyer's payment obligation was not extinguished by the return of the funds, and that the Client could still pursue the buyer.

But the court's reasoning was this: as long as the agent is at fault and that fault is causally linked to the principal's loss, the agent must compensate the loss. Whether the principal can recover it elsewhere is a separate matter.

That is how "risk transfer" really works: it is not that the client deliberately pushes risk onto you, but that one fault of yours becomes the legal channel through which downstream risk flows to you. Once that channel opens, what you bear is no longer the small risk of your own service fee but the risk of the client's entire transaction.

3. Both sides used a "default process" instead of an "explicit instruction"

Looking back, there were three moments when both sides could have made things clear, and neither did:

  • At signing: The Client did not say "I need to declare in my own name in order to receive foreign exchange." We did not say "under the door-to-door, duties-included model, you will not get a declaration in your name."
  • Before shipment: We did not confirm the declaration method with the forwarder, and did not tell the Client the result.
  • When first asked: We replied "I'll ask" in an instant message, without a written conclusion and without escalation.

The Client assumed "customs clearance" naturally included giving it the customs declaration. We assumed "customs clearance" meant getting the goods through customs lawfully. Both readings are plausible, but the court ultimately measured us against the duty of care of a professional agent. In a relationship with an asymmetry of expertise, the responsibility for spelling things out falls mainly on the professional side.

Quick Reference to the Law: Provisions Clients and Service Providers Should Know

The provisions below are those actually involved in the judgment, the parties' arguments and our lawyers' analysis, organised by purpose. This section is a risk notice only and does not constitute legal advice. Consult a practising lawyer for specific questions.

Contracts and liability

  • Civil Code, Article 929 (fault-based liability in paid entrustment): In a paid entrustment, an agent whose fault causes loss to the principal must compensate. This was the core basis of the judgment.
  • Civil Code, Article 509 (full performance and good faith): The parties must fully perform their obligations as agreed, and perform duties of notice, assistance and confidentiality according to the nature and purpose of the contract and trade practice. The "duty of notice" is exactly what we failed to fulfil.
  • Civil Code, Articles 577 and 584 (liability for breach and the foreseeability rule): Damages equal the loss caused by the breach, but may not exceed the loss that the breaching party foresaw or ought to have foreseen when the contract was made. The court held that we "ought to have known" that foreign exchange receipt was needed, which put the loss within the foreseeable range.
  • Civil Code, Article 591 (duty to mitigate loss): After a breach, the other party must take appropriate measures to prevent the loss from growing. In the proceedings we argued that the Client had the remittance returned within ten days and did not adopt alternative arrangements, but the court did not accept this argument.
  • Civil Code, Article 142 and Article 2 of the Judicial Interpretation on the General Provisions of the Contract Part (contract interpretation and trade practice): The meaning of contract terms is determined by reference to the wording, nature, purpose and trade practice. We argued that "duties-included double clearance" is industry practice, but the court held there was no evidence that the parties had agreed to this declaration method. Industry practice cannot replace an explicit agreement.

Customs and declarations

  • Customs Law, Article 24: The shipper of exported goods must declare truthfully to Customs.
  • Customs Law provisions on customs declaration agents: A party that entrusts a customs broker must give the broker truthful information about the entrusted matters, and the broker must submit a power of attorney to Customs.
  • National standard Service Specification for Customs Declaration Agency (GB/T 37518-2019): A customs declaration entity should sign an agency declaration authorisation or an entrusted declaration agreement with the principal.
  • National standard Logistics Terminology (GB/T 18354-2021): It defines "customs clearance" as completing all the formalities required for import or export clearance. We cited this definition to argue that "clearance was completed," but it does not answer the question "clearance in whose name?"

Foreign exchange and receipts

  • Regulations on Foreign Exchange Administration, Article 12: Current-account foreign exchange receipts and payments must rest on a genuine and lawful transaction, and financial institutions must review the authenticity of transaction documents and their consistency with the foreign exchange receipts and payments.
  • The basic logic of foreign exchange control for trade in goods: In principle, the party receiving the export proceeds, the domestic shipper on the customs declaration and the actual trading party should be the same. If the name on the customs declaration is not the exporter, it is hard to show the bank that the foreign exchange corresponds to a genuine export.

Five Points Where We Could Have Stopped the Loss

Had we been able to turn back time, getting any one of these points right would have changed the outcome completely.

Point 1: At quotation, we sold "duties-included double clearance" as a price advantage without stating its documentary consequence

"Door-to-door, duties-included, double clearance" is a selling point in a quotation: cheap and hassle-free. But we did not write one equally important sentence: "This model does not provide an export customs declaration naming your company as shipper. If you need one for foreign exchange receipt or tax refund, please choose a separate declaration option, charged separately." That one sentence would have let the Client choose before signing.

Point 2: We signed a clause we could not honour

The phrase "proof of receipt sufficient for the Client's payment collection" was understood at the time as a signed receipt or delivery note. But the words "for payment collection" were exactly what brought the Client's need to collect payment into our contractual obligations. Any clause containing wording like "meets the Client's requirements" or "acknowledged by the end user" should prompt the question: which exact document, issued by whom, in whose name? If you cannot answer, do not sign.

Point 3: The subcontractor's deliverables were not aligned with our commitment to the client

What we promised the Client was "logistics and customs clearance," yet when placing the order with the forwarder we did not specify the declaration method. In a subcontracting chain, the deliverables of the downstream contract must be at least equal to what you promised upstream, or you bear the whole gap in between.

Point 4: When first asked, we did not escalate

When the Client first asked for the customs declaration, less than a month had passed since shipment, and the forwarder could very likely still have remedied it or given a clear answer. But the request stayed in a front-line colleague's instant messages, with no ticket, no written conclusion and no report to management. By the time the remittance arrived five months later, it could no longer be fixed.

Point 5: After the dispute arose, our proposals looked like evasion to the Client

After the dispute arose we proposed alternatives, such as the Client authorising our overseas affiliate to collect the payment and then forward it, or the Client explaining the situation to the bank itself. From a compliance standpoint these were not necessarily infeasible, but to the Client they meant changing its payment route and taking on extra compliance risk. The better approach would have been to confirm the facts in writing immediately, acknowledge the problem, and offer a remedy at our own cost. No lawyer's proposal or carefully drafted settlement letter at the litigation stage is as useful as one written reply when the dispute first appears.

For IT Service Providers: An Operational Risk Checklist You Can Use Directly

These practices apply not only to logistics and customs declaration but to every "while we're at it" non-core service, such as procurement on behalf of the client, paying on its behalf, handling permits, managing third-party accounts, or signing for deliveries.

Contract and scope

  • Separate non-core services. Give logistics, customs, procurement and payment their own sections with clear boundaries. Where the client can contract directly with a specialist provider, avoid subcontracting.
  • Define industry terms. For "customs clearance," "delivery," "acceptance," "go-live" and "migration complete," state what is included, what is not, which documents are delivered, and in whose name they are issued.
  • Ask about downstream use. Before signing, always ask: "What will you use the result of this service for next?" Foreign exchange receipt, tax refund, audit, insurance, asset booking and regulatory filing each require different documents.
  • Agree a liability cap, but do not count on it as a safety net. You may cap compensation at the service fee and exclude indirect loss. But standard terms must be brought to the other party's attention in a reasonable manner, or they may not become part of the contract, and an exclusion clause is void where it covers property loss caused by intent or gross negligence.

Performance and subcontracting

  • State the key method of execution in the subcontract order. The declaration method, the shipper's name and the list of documents to be delivered must be written into the instruction to the subcontractor.
  • Confirm and notify before shipment. Once the key method of execution is fixed, notify the client in writing. If the client does not agree, adjust before shipment.
  • Deliver documents with the delivery. Put document delivery on the completion acceptance checklist rather than waiting for the client to ask.

Communication and evidence

  • Turn out-of-contract or compliance requests into tickets. When a client raises a need relating to documents, compliance or payment through any channel, the recipient must convert it that day into a ticket or formal email, with a written reply and a timeline from the responsible person.
  • Email over instant messaging. Instant messaging suits coordination, not confirmation. What helped us secure the additional charges in this case was one email and the Client's written reply the same day.
  • Preserve key evidence promptly. Emails and chat records can be preserved by methods such as trusted timestamps, so that you do not discover at trial that the original medium is gone.

Accounts receivable

  • Beware of "deferred payment" clauses. A clause such as "payment may be deferred if the requirements of the Client or end user are not met" lets the client lawfully withhold the entire balance during a dispute. At signing, make "requirements" specific, or limit the scope of deferral.
  • Do not sleep on your rights. Chase overdue receivables in writing on time. In the proceedings the other side used our three years without a payment demand to argue that we knew we were in the wrong.

For Clients: How to Raise Requirements Through Proper Channels and Write Clear Instructions

This section is for our clients, and for any business that entrusts work to an IT service provider.

Why use proper channels

In this case, the most critical request was made in an instant message between project staff. It had no number, no owner, no deadline, and nobody gave a written reply. For the client, that meant the request never really entered the provider's processing workflow. For the provider, it meant the problem was never seen.

Please submit requirements through one of the following channels, and keep the reference number:

  • Service desk or ticketing system: Handled 24/7, with every request given a number, an owner and a response time.
  • Your account consultant's work email: Suited to out-of-contract requests, scope changes and compliance document needs.
  • Formal written letter: Suited to disputes, claims and payment objections.

Instant messaging can be used for reminders and coordination, but alongside a reminder, please submit the request through one of the channels above.

Six elements of an instruction

An instruction that can be executed accurately should answer at least six questions:

  • What: The specific matter, for example "ship a batch of network equipment from our domestic warehouse to a designated overseas data centre and complete clearance at both ends."
  • In whose name: For example, "export declaration must name our company as the domestic shipper." In this case, that one line was worth about RMB 300,000.
  • Deliver what: List the documents you need, with the name on them, the number of copies and the format, for example "an export declaration naming our company as shipper, an air waybill naming our company as consignor, and a destination proof of receipt."
  • For what purpose: State the purpose, for example "for export foreign exchange receipt and export tax refund." Once the purpose is written down, the provider can tell which methods of execution are not workable.
  • By when: State the delivery deadline and the document delivery deadline separately.
  • How to accept: The acceptance criteria and the acceptor, plus the materials you need to provide, such as an agency declaration authorisation, electronic port platform authorisation confirmation, the sales contract and invoices.

Vague wording versus clear wording

  • Vague: "Provide logistics and customs clearance services, door to door, by air."
  • Clear: "Provide door-to-door air freight logistics. The export declaration must be filed separately with our company as the domestic shipper; consolidated declaration is not accepted. Within 5 working days after the goods are released, deliver electronic copies of the export declaration and the air waybill for export foreign exchange receipt. We will provide an agency declaration authorisation 3 working days before shipment."

With the first wording, each side can hold its own interpretation. With the second, the provider knows at the quotation stage which model to choose, what it costs and what the client must contribute.

What to do when you disagree

  • Write first, then talk. State the facts, your request and the time limit you expect in an email or letter, then follow up by phone.
  • Require a written reply. The provider should give a written conclusion within the agreed time, including whether a remedy is possible, how it would work and who bears the cost.
  • Follow the escalation path. If the front line cannot resolve it, escalate to the account consultant and the service owner.
  • Keep evidence and stop the loss early. Raising the issue while it can still be fixed usually protects your interests better than a claim afterwards.

How We Are Improving

After this loss, our direction is simple. For non-core matters such as customs declaration, procurement and payments on behalf of clients, we will not handle them ourselves where the client can contract directly with a specialist provider. Where we must handle them, the contract will state the method of execution and the document list, and the documents will be part of acceptance. Every compliance-related request, whichever channel it arrives through, will be converted into a ticket and answered in writing.

If you are evaluating IT service providers, or want to clarify the scope and deliverables of your current services, you are welcome to contact us with your requirements. You can also see how our 24/7 help desk, managed IT and cloud services and IT infrastructure deployment services define scope and deliverables.

FAQ

The goods were delivered and the buyer paid. Why must the service provider still pay compensation?

The court looks at whether the agent was at fault and whether the fault caused loss. Delivery of the goods proves only that logistics was completed. The Client could not receive foreign exchange because it lacked a customs declaration naming itself as shipper, and the court found a causal link between that and the declaration method the provider used.

Does "customs clearance" necessarily include providing a customs declaration in the client's name?

Not necessarily, as a concept. But in this case the contract provided for "proof sufficient for the Client's payment collection," the provider held import and export qualifications, and it had not told the Client the declaration method in advance. The court therefore held that the provider should have foreseen the need to receive foreign exchange.

Is consolidated declaration or "duties-included double clearance" illegal?

This article does not assess the model itself. The judgment in this case held that consolidated declaration made the declaring entity inconsistent with the real trading party and left the Client unable to receive the foreign exchange. An exporter that needs to receive foreign exchange or claim a tax refund must understand its documentary consequences in advance.

The client did not ask for a separate declaration and did not issue an authorisation. Does that reduce the provider's liability?

We made this argument at both instances, and it was not accepted. The court held that the responsibility to alert and to ask falls mainly on the party providing the professional service.

Can a service provider avoid this kind of risk with a liability cap clause?

It should agree one, but cannot rely on it entirely. Standard terms must be brought to the other party's attention in a reasonable manner, and an exclusion clause is void where it covers property loss caused by intent or gross negligence.

As a client, through which channel should I raise a document or compliance requirement?

Through a service desk ticket, your account consultant's work email or a formal letter, stating the matter, the name, the deliverables, the purpose, the deadline and the acceptance criteria.

Conclusion

This lawsuit cost us far more than the contract value. We respect the final judgment, and we have paid in full.

Looking back, the part of this project we do best, cross-border IT infrastructure deployment and onsite IT support, was completed successfully, as the client, the end user and the court all confirmed. The cost came from the part we should not have taken on casually and did not define clearly.

We wrote this up because we believe professionalism in managed IT services is shown not only in installing the equipment and getting the system running, but also in setting clear boundaries, delivering the documents, and treating every seemingly casual request as a formal instruction.

We hope this review will lead clients to add one more line when stating requirements, "in whose name, and for what purpose," and lead our peers to ask one more question before taking on the next "while we're at it" job: "If this goes wrong, can I bear it?"

Share:

Ready to take action?

Turn these insights into a roadmap for your business.

Book a 15-minute no-obligation consultation with our APAC IT experts. We'll review your current setup and provide a tailored IT roadmap within 24 hours.

📋

Free Checklist

10 Critical Checks Before Expanding IT to Greater China

PIPL compliance, network segmentation, bilingual helpdesk setup, and more — everything your IT team needs before Day 1 in China.

Request the checklist →