Global Luxury Fashion Brand — Cisco Meraki Switch, Firewall & Wi-Fi Rollout Across 153 APAC Boutiques in 13 Countries
Client Case Luxury Retail · Fashion Multi-Country Meraki Rollout & Retail PMO

Global Luxury Fashion Brand — Cisco Meraki Switch, Firewall & Wi-Fi Rollout Across 153 APAC Boutiques in 13 Countries

Turnkey multi-country network modernisation deploying Cisco Meraki firewalls, switches, and access points across 153 luxury retail boutiques in 13 APAC countries—uniting centralised procurement, door-to-door logistics, Ekahau site surveys, pre-delivery staging, overnight installation, UAT, and ongoing maintenance.

153

APAC Retail Boutiques

13

Countries Delivered

15 Mos

Feb 2020 – Apr 2021 Rollout

5

Integrated Vendor Streams

EXECUTIVE PROJECT SUMMARY

A leading global luxury fashion house needed to modernise retail networking across 153 APAC boutiques spanning 13 countries—including Shanghai, Hong Kong, Tokyo, Singapore, Manila, Jakarta, and seven additional regional markets—between February 2020 and April 2021. Brocent ran the end-to-end programme through a single APAC Project Management Office (PMO), coordinating centralised procurement, five integrated vendor streams, door-to-door cross-border logistics, per-store Ekahau RF site surveys, off-site Cisco Meraki staging, after-hours boutique installation (with Mainland China stores executed via BROCENT Group affiliates), formal UAT sign-off, and ongoing maintenance.

Luxury Retail · Fashion Shanghai Multi-Country Meraki Rollout & Retail PMO Feb 2020 – Apr 2021
Stella Chao — Senior vCIO · Retail, Manufacturing & Global Expansion IT
Technically Reviewed By · Stella Chao

Senior vCIO · Retail, Manufacturing & Global Expansion IT

20+ Yrs Retail & Manufacturing IT · Multi-Site Store Cabling & Ops · ITIL & PMP Global Delivery

View leadership profile →

13-COUNTRY CISCO MERAKI RETAIL ROLLOUT & UAT MATRIX

Standardised boutique deployment gates enforced across all 153 APAC stores

Ekahau Wireless Site Survey

Engineering Scope: Pre-install RF attenuation & heatmapping in every boutique
Quality Standard: Full sales-floor & stockroom coverage for mPOS & scanners
Sign-Off Evidence: Store-specific Ekahau heatmap & AP mounting plan

Procurement & Door-to-Door Logistics

Engineering Scope: Centralised sourcing, customs IOR & last-mile delivery across 13 countries
Quality Standard: Serial-tracked delivery aligned to mall work-permit dates
Sign-Off Evidence: Customs clearance proof & store receiving sign-off

Off-Site Technical Staging

Engineering Scope: Cisco Meraki MX firewall, MS switch & MR AP pre-configuration
Quality Standard: Firmware locked, cloud-claimed & port-labelled pre-dispatch
Sign-Off Evidence: Staging QA checklist & Meraki Dashboard serial mapping

Onsite Cutover & Store UAT

Engineering Scope: After-hours rack swap, AP install, POS & Wi-Fi validation
Quality Standard: Zero trading-hour downtime + clean back-of-house cabling
Sign-Off Evidence: Signed store UAT pack, speed/roaming logs & rack photos

IT MANAGER EVALUATION & AUDIT BENCHMARKS

Luxury Retail Network Rollout Governance Across 13 APAC Jurisdictions

Cisco Meraki Cloud Standards · Ekahau RF Validation · Formal Store UAT

NO FLY-IN ENGINEERS REQUIRED

In-Country Field Delivery Across All 13 Markets

Executing during 2020–2021 border closures proved the resilience of Brocent's local APAC field network and BROCENT Group Mainland China affiliate teams.

PLUG-AND-PLAY CUTOVER SPEED

100% Off-Site Meraki Technical Staging

Pre-configuring every MX, MS, and MR device before shipment compressed overnight mall cutovers and eliminated configuration errors at 03:00 AM.

LUXURY-GRADE EXECUTION

Ekahau RF Precision + Invisible Boutique Aesthetics

AP placements balanced flawless clienteling and mPOS roaming with strict luxury retail ceiling-design rules enforced by store architects.

UNIFIED POST-ROLLOUT SUPPORT

Seamless Handover Into Ongoing Maintenance

Every completed boutique entered ongoing maintenance with full serial inventory, UAT photos, and local break-fix dispatch readiness.

IT Manager Field Note: In multi-country retail network rollouts, 80% of schedule slippage happens before an engineer ever walks into a store—at customs clearance, mall permit sign-off, or unconfigured hardware arrival. Combining centralised procurement, off-site staging, and a single APAC PMO eliminates all three failure points.

01 · PROJECT CONTEXT & CHALLENGES

What the client started with and needed to achieve

PROGRAMME SCALE

153 Luxury Boutiques · 13 APAC Countries · 15 Months

Flagship street boutiques, luxury mall concessions, and travel-retail outlets across Shanghai, Hong Kong, Tokyo, Singapore, Manila, Jakarta, and 7 other APAC markets delivered between Feb 2020 and Apr 2021.

DELIVERY & PMO ARCHITECTURE

Single APAC PMO + Local Country Field Teams (CN via BROCENT Group)

One programme office managed 5 vendor/logistics streams, mall permits, customs clearance, and in-country engineering dispatch—executing Shanghai and Mainland China stores via BROCENT Group affiliate entities.

RETAIL TRADING CONSTRAINT

Zero Lost Trading Hours · Luxury Aesthetic & RF Precision

All physical cabling, rack swaps, and AP mounting had to finish inside narrow after-hours mall windows with zero visible cabling and 100% POS/clienteling uptime at next-morning store opening.

KEY CHALLENGES & TRIGGERS

  • Executing simultaneous network cutovers across 153 luxury boutiques in 13 APAC jurisdictions amid pandemic border closures and strict mall after-hours access windows
  • Coordinating cross-border hardware procurement, customs clearance, and door-to-door logistics across five aligned vendor and carrier streams without delaying store trading
  • Eliminating Wi-Fi dead zones across marble, glass, and multi-floor boutique interiors where mobile POS, clienteling tablets, and inventory scanners cannot drop sessions

02 · DELIVERY WORKFLOW & ARCHITECTURE

Layered reference topology — select any zone or stage

Multi-Country Meraki Rollout & Retail PMO HK · SG · CN · JP
Active / Primary Path Verified Rollback / HA
ZONE 01 · EDGE & INGRESS 01 13 Countries · 5 Vendor… Centralised APAC PMO & Multi-Country Logistics Streams Shanghai · Hong Kong · Tokyo Primary Path Active · Audited Rollback Gate Pre-tested HA ZONE 02 · CORE & CONTROL PLANE 02 Ekahau · Boutique RF… Ekahau Wireless Site Survey & RF Design Cisco Meraki MX / MS / MR 03 Cisco Meraki MX · MS · MR Pre-Delivery Technical Staging & Cloud Provisioning Ekahau Wireless Site Surveys ZONE 03 · PRODUCTION & DELIVERY 04 Zero Store Downtime… After-Hours Installation, UAT & Ongoing Maintenance 13-Country Procurement & Verified Outcome 153 APAC Retail Boutiques 13 Countries Delivered 24×7 ITIL NOC · ISO/IEC 27001 GOVERNANCE & AUDIT TELEMETRY Cisco Meraki Cloud Standards
Layered reference topology — unified typography, active/standby routing & 24×7 governance plane Click any node above or tab below to inspect engineering details
01 Centralised APAC PMO & Multi-Country Logistics · 13 Countries · 5 Vendor Streams

A dedicated Brocent PMO synchronised brand HQ IT, mall property teams, hardware procurement, customs brokers, and local country engineers across 13 APAC markets—tracking all 153 boutiques on one live wave-rollout schedule despite 2020–2021 travel restrictions.

FIELD EXECUTION SNAPSHOTS

Three-stage visual delivery walkthrough

01 / 03
13-country PMO launch, Ekahau RF surveys & centralised sourcing
WAVES 1–2

13-country PMO launch, Ekahau RF surveys & centralised sourcing

Established a central PMO governing all 153 store schedules, completed Ekahau wireless site surveys per boutique, and executed centralised hardware procurement and IOR/door-to-door logistics.

03 · IMPLEMENTATION NARRATIVE

How our engineers executed and verified this engagement

01

Programme Kickoff, Central Procurement & 13-Country Logistics (Q1 2020)

Brocent launched the central APAC PMO in February 2020, harmonising five vendor and supply-chain streams to source Cisco Meraki MX/MS/MR hardware, clear country-specific customs/compliance rules, and align deliveries with mall access calendars across 13 countries.

02

Per-Boutique Ekahau Wireless Site Surveys & Blueprint Sign-Off

Local engineers conducted Ekahau site surveys across boutiques in Shanghai, Hong Kong, Tokyo, Singapore, Manila, Jakarta, and seven other APAC markets—validating RF propagation through luxury finishes and finalising concealed AP mounting points with store operations.

03

Regional Staging Hubs & Wave-Based Overnight Store Cutovers

Each wave's Meraki kits underwent off-site firmware standardisation, template binding, and burn-in testing before door-to-door delivery. Overnight engineering teams—including BROCENT Group affiliates across Mainland China—swapped legacy switches/firewalls and mounted APs without disrupting trading hours.

04

153-Store UAT Completion & Transition to Ongoing Maintenance (Apr 2021)

Every boutique closed with formal UAT sign-off covering POS transactions, staff/guest Wi-Fi roaming, firewall failover, and as-built rack photos. By April 2021, all 153 APAC stores were live on Cisco Meraki and transitioned smoothly into ongoing maintenance.

04 · PRACTICAL RISKS & MITIGATION

4 issues that typically go wrong—and how we prevented them

Cross-Border Customs Delays or Equipment Shortages Across 13 Countries

Centralised procurement and IOR door-to-door logistics under one PMO with early country-compliance checks and buffer stock tracking.

Overnight Cutover Overrunning Into Morning Luxury Store Opening

Pre-staged and cloud-claimed all Cisco Meraki gear off-site and enforced clear rollback checkpoints during mall after-hours windows.

Wi-Fi Dead Spots Impacting Mobile POS and Clienteling Tablets

Mandated Ekahau wireless site surveys before installation and post-cutover roaming/throughput verification during UAT.

Pandemic Travel Bans Blocking Regional Deployment Engineers

Leveraged established in-country field engineers across all 13 markets—including BROCENT Group affiliates in Mainland China—eliminating cross-border travel dependency.

05 · RESPONSIBILITY, DELIVERABLES & SPECS

Clear split between Brocent and client IT

BROCENT APAC PMO & LOCAL TEAMS (CN VIA BROCENT GROUP) HANDLE

  • Central PMO scheduling across 153 boutiques in 13 APAC countries & 5 vendor streams
  • Centralised hardware procurement, customs coordination & door-to-door logistics
  • Per-store Ekahau wireless site surveys & off-site Cisco Meraki technical staging
  • After-hours onsite installation (Mainland China via BROCENT Group affiliates), UAT & ongoing maintenance

CLIENT GLOBAL / APAC RETAIL IT RETAIN

  • Cisco Meraki Dashboard master organisation, security templates & VLAN standards
  • Approval of boutique wave priorities, mall landlord permits & aesthetic AP placement
  • Ownership of Meraki licences, hardware assets & local ISP circuit contracts
  • Final UAT acceptance sign-off per store and ongoing service governance

DOCUMENTS & AUDIT RECORDS HANDED OVER

13-Country Wave Rollout Master Schedule & PMO Weekly Status Packs
153 Boutique-Specific Ekahau Wireless Site Survey & RF Heatmap Reports
Centralised Procurement, Customs & Serial-Level Logistics Register
Pre-Delivery Cisco Meraki Technical Staging & Firmware QA Logs
153 Signed Store UAT Packs with As-Built Rack & AP Photographs
Post-Rollout APAC Retail Maintenance Runbook & Asset Inventory

ENVIRONMENT & CONTRACT SUMMARY

Location / Facility
Shanghai, Hong Kong, Tokyo, Manila, Singapore, Jakarta + 7 more APAC countries
Scenario
Multi-Country Meraki Rollout & Retail PMO
Timeframe
Feb 2020 – Apr 2021
Delivery Model
Central APAC PMO + local field teams (Mainland China via BROCENT Group affiliates)
Contracting Entity
Brocent Hong Kong / Singapore HQ (HKD / SGD / USD; Mainland China delivered locally via BROCENT Group affiliates)

06 · MEASURED RESULTS & OUTCOMES

Before vs. after operational impact

Multi-Country Rollout Governance
Before Fragmented country contractors with incompatible schedules
After Single APAC PMO delivering all 153 stores across 13 countries on schedule
Boutique Wireless & POS Stability
Before Unverified AP placement causing mobile POS drops on peak weekends
After Ekahau-validated Cisco Meraki Wi-Fi & full-store UAT sign-off
Cross-Border Logistics & Staging
Before Raw boxes shipped to stores requiring slow onsite configuration
After Pre-staged, plug-and-play Meraki kits delivered door-to-door

“Deploying Cisco Meraki across 153 luxury boutiques in 13 APAC countries during 2020–2021 without missing trading hours required extraordinary PMO discipline, staging rigour, and local field execution—Brocent delivered every single store.”

— APAC Retail IT Director · Global Luxury Fashion Brand

INCLUDED IN SCOPE

Cisco Meraki MX / MS / MR Ekahau Wireless Site Surveys 13-Country Procurement & Logistics Pre-Delivery Technical Staging Overnight Install & Store UAT Central APAC PMO & Maintenance

PLANNING A SIMILAR PROJECT?

Multi-Country Retail Network Rollout, Staging & Ekahau Surveys · APAC

Share your target cities, headcount, and timeline for a scoped SLA and transparent rate card.

EXECUTIVE BRIEF · 2-PAGE A4 PDF

Unlock the 2-page Executive Brief PDF

Read the complete interactive case study on this page, or enter your business details below to immediately unlock the formatted 2-page A4 PDF for offline boardroom sharing.

07 · FREQUENTLY ASKED QUESTIONS

Key technical & commercial questions before starting

How did Brocent execute across 13 APAC countries during 2020–2021 travel restrictions?

A central APAC PMO coordinated established in-country field engineering teams—including BROCENT Group affiliates in Mainland China—paired with centralised procurement, door-to-door logistics, and off-site pre-staging, requiring zero cross-border engineer travel.

Why run an Ekahau wireless site survey in every luxury retail boutique?

Luxury stores use marble, mirrors, glass, and metal displays that heavily attenuate Wi-Fi signals. Ekahau surveys guarantee seamless mobile POS and clienteling coverage while respecting strict architectural concealment guidelines.

What happens during off-site technical staging before store delivery?

Every Cisco Meraki MX firewall, MS switch, and MR access point is unboxed, upgraded to target firmware, claimed into the store's Meraki template, tested, and labelled so onsite installation finishes cleanly within tight mall night windows.

Does Brocent support ongoing maintenance after the multi-country rollout finishes?

Yes. Following formal UAT sign-off at all 153 stores, Brocent transitioned the full APAC store estate into ongoing maintenance and local break-fix dispatch.