Germany-Based Industrial Manufacturer — 14-Month Multi-Site Campus Data Centre Build & SIEM Across China & Hong Kong
Client Case Industrial Manufacturing Campus Data Centres, Multi-Vendor Build & SIEM

Germany-Based Industrial Manufacturer — 14-Month Multi-Site Campus Data Centre Build & SIEM Across China & Hong Kong

End-to-end IT architecture design (HLD & LLD), 14-month campus data centre construction, structured cabling, wireless simulation, power estimation, cybersecurity/SIEM deployment, and hybrid cloud integration across Shanghai, Beijing, Guangzhou, and Hong Kong using Aruba, Cisco, Barracuda, APC, and HPE.

4 Sites

SH · BJ · GZ · HK Campuses

14 Mos

Campus DC Build Programme

5 Vendors

Aruba·Cisco·Barracuda·APC·HPE

3+ Yrs

Feb 2019 – Apr 2022 Lifecycle

EXECUTIVE PROJECT SUMMARY

A global German industrial manufacturer expanding APAC production capacity engaged Brocent from February 2019 through April 2022—spanning a 14-month build phase plus ongoing maintenance—to design and construct campus data centres across Shanghai, Beijing, Guangzhou, and Hong Kong in full alignment with headquarters in Germany. Coordinating five major OEM stacks (Aruba, Cisco, Barracuda, APC, and HPE) with Mainland China campus construction delivered through BROCENT Group affiliate entities, Brocent delivered complete HLD/LLD blueprints, structured cabling, power estimation, wireless simulation, cybersecurity and SIEM implementation, and hybrid cloud integration.

Industrial Manufacturing Shanghai Campus Data Centres, Multi-Vendor Build & SIEM Feb 2019 – Apr 2022 (14 months build + ongoing)
L.J. Yu — Senior vCIO · Infrastructure & Wireless
Technically Reviewed By · L.J. Yu

Senior vCIO · Infrastructure & Wireless

Equinix IBX Data Centres · Structured Cabling · Ekahau Wireless Architecture

View vCIO profile →

4-SITE CAMPUS DATA CENTRE & MULTI-VENDOR ENGINEERING MATRIX

Integrated design, physical build, and security verification across China and Hong Kong

Architecture & Power Sizing

OEM Stack & Design Scope: Full HLD & LLD, APC UPS/PDU load & thermal estimation
Build Standard: N+1 APC power redundancy & German HQ engineering sign-off
Handover Deliverable: Approved HLD/LLD binders & APC power calculation sheets

Structured Cabling & Wireless

OEM Stack & Design Scope: Campus copper/fibre structured cabling & Aruba RF simulation
Build Standard: Certified patch testing + predictive & validation Wi-Fi heatmaps
Handover Deliverable: Fluke cable test reports & Aruba wireless coverage maps

Core Network, Compute & Storage

OEM Stack & Design Scope: Cisco switching/routing + HPE ProLiant servers & storage
Build Standard: Dual-path core resilience & standardised rack elevation
Handover Deliverable: As-built rack elevations, port tables & HPE burn-in logs

Cybersecurity, SIEM & Hybrid Cloud

OEM Stack & Design Scope: Barracuda firewalls, SIEM log pipelines & hybrid cloud links
Build Standard: Centralised event correlation visible to Germany HQ SOC
Handover Deliverable: SIEM ingestion proof, security ruleset & maintenance runbook

IT MANAGER EVALUATION & AUDIT BENCHMARKS

German Manufacturing IT Standards & Multi-Vendor Campus Governance

HLD/LLD Engineering Sign-Off · 5-Vendor Integration · HQ-Aligned SIEM

HQ-GRADE DOCUMENTATION

Full HLD & LLD Before First Cable Pull

German industrial IT teams expect blueprint precision before construction starts. Delivering rigorous HLD/LLD and power estimates prevented costly mid-build rework across all four sites.

FIVE VENDORS, ONE ACCOUNTABLE PMO

Aruba · Cisco · Barracuda · APC · HPE Unified

Managing five OEMs across four cities under one Brocent PMO eliminated scheduling collisions between facilities, cabling, power, server, and security teams.

BUILT-IN CYBER & SIEM VISIBILITY

Barracuda + SIEM Integrated Day One

Rather than bolting security on after factory commissioning, Barracuda appliances and SIEM logging were engineered into the core campus build from day one.

SMOOTH TRANSITION TO OPERATIONS

14-Month Build + Continuous Multi-Year Maintenance

The same teams who built the racks across China (via BROCENT Group affiliates) and Hong Kong remained accountable for ongoing maintenance and hybrid cloud stability.

IT Manager Field Note: European manufacturers expanding in China frequently struggle when local fit-out contractors handle cabling and power separately from network, server, and security integrators. Unifying HLD/LLD, APC power, structured cabling, 5 OEMs, and SIEM under one PMO keeps German HQ standards intact on every shop floor.

01 · PROJECT CONTEXT & CHALLENGES

What the client started with and needed to achieve

MANUFACTURING FOOTPRINT

4 APAC Campuses (SH, BJ, GZ, HK) · HQ in Germany

Expanding industrial production plants and regional hubs requiring resilient local server rooms, deterministic factory Wi-Fi, clean APC power redundancy, and direct alignment with German headquarters IT.

CONTRACT & DELIVERY MODEL

14-Month Turnkey PMO Build + Ongoing Maintenance

Brocent governed architecture, Hong Kong site delivery, and German HQ technical reporting, while BROCENT Group affiliate teams executed campus builds and ongoing maintenance across Shanghai, Beijing, and Guangzhou.

MULTI-VENDOR & SECURITY MANDATE

5 OEMs (Aruba · Cisco · Barracuda · APC · HPE) + SIEM

Zero shortcuts on German industrial standards—requiring formal HLD/LLD sign-off, power/thermal calculations, Barracuda perimeter security, SIEM log ingestion, and hybrid cloud integration.

KEY CHALLENGES & TRIGGERS

  • Translating strict German engineering HQ data-centre, power, and cybersecurity specifications into compliant physical builds across four Greater China manufacturing and office campuses
  • Integrating five distinct technology stacks—Aruba wireless/access, Cisco routing/switching, Barracuda security, APC power/UPS, and HPE servers/storage—under one accountable PMO
  • Delivering certified structured cabling, factory-floor wireless simulation, SIEM visibility, and hybrid cloud connectivity within a 14-month expansion timeline followed by multi-year maintenance

02 · DELIVERY WORKFLOW & ARCHITECTURE

Layered reference topology — select any zone or stage

Campus Data Centres, Multi-Vendor Build & SIEM CN · HK · EU
Active / Primary Path Verified Rollback / HA
ZONE 01 · EDGE & INGRESS 01 HLD · LLD · APC Power… German-HQ-Aligned HLD/LLD & Power Estimation HLD & LLD IT Architecture Shanghai · Beijing Primary Path Active · Audited Rollback Gate Pre-tested HA ZONE 02 · CORE & CONTROL PLANE 02 Structured Cabling · Aruba… Structured Cabling & Campus Wireless Simulation HLD & LLD IT Architecture 03 Cisco · HPE · Barracuda… Multi-Vendor Core Compute, Network & Security Build Aruba / Cisco / Barracuda / APC / ZONE 03 · PRODUCTION & DELIVERY 04 SIEM · Hybrid Cloud… SIEM Implementation, Hybrid Cloud… Structured Cabling & Power Verified Outcome 4 Sites SH · BJ · GZ · HK Campuses 14 Mos Campus DC Build Programme 24×7 ITIL NOC · ISO/IEC 27001 GOVERNANCE & AUDIT TELEMETRY HLD · LLD Engineering Sign-Off
Layered reference topology — unified typography, active/standby routing & 24×7 governance plane Click any node above or tab below to inspect engineering details
01 German-HQ-Aligned HLD/LLD & Power Estimation · HLD · LLD · APC Power Sizing

Brocent solution architects produced exhaustive High-Level and Low-Level Designs for all four campuses, calculating kVA power budgets, APC UPS runtime, BTU heat dissipation, and rack layouts for formal review by headquarters in Germany before procurement began.

FIELD EXECUTION SNAPSHOTS

Three-stage visual delivery walkthrough

01 / 03
Full IT architecture design, power estimation & wireless simulation
MONTHS 1–3

Full IT architecture design, power estimation & wireless simulation

Authored German-HQ-approved High-Level and Low-Level Designs (HLD/LLD), APC power/cooling load calculations, structured cabling blueprints, and campus wireless RF simulations across all 4 sites.

03 · IMPLEMENTATION NARRATIVE

How our engineers executed and verified this engagement

01

HLD/LLD Architecture, Power Estimation & Wireless Simulation (Feb–May 2019)

Working directly with headquarters engineers in Germany, Brocent authored complete HLD and LLD documentation for Shanghai, Beijing, Guangzhou, and Hong Kong—covering APC UPS load sizing, structured cabling pathways, Aruba wireless simulations, and five-vendor BOM validation.

02

Four-Site Physical Build: Cabling, APC Power & HPE/Cisco Core (Months 4–11)

BROCENT Group affiliate construction teams in Shanghai, Beijing, and Guangzhou alongside Brocent Hong Kong executed certified structured cabling, APC rack/UPS installation, HPE server and storage commissioning, and Cisco/Aruba network bring-up.

03

Barracuda Cybersecurity, SIEM & Hybrid Cloud Integration (Months 12–14)

In the final phase of the 14-month build, engineers hardened campus perimeters with Barracuda firewalls, onboarded multi-vendor logs into SIEM, and connected local campus clusters with the group's hybrid cloud architecture.

04

Multi-Year Ongoing Maintenance & Operational Governance (2020 – Apr 2022)

Following formal four-site commissioning, Brocent transitioned the entire estate into ongoing maintenance—delivering preventive inspections, firmware lifecycle management, and rapid local break-fix across all four campuses.

04 · PRACTICAL RISKS & MITIGATION

4 issues that typically go wrong—and how we prevented them

Design Mismatch Between German HQ Standards and Local Campus Reality

Enforced formal HLD/LLD, power estimation, and wireless simulation sign-off with Germany HQ before local procurement or cabling began.

Integration Failures Across Five Separate OEM Vendors

Consolidated Aruba, Cisco, Barracuda, APC, and HPE engineering under one PMO with end-to-end interoperability testing prior to handover.

Undersized Server-Room Power or Uncertified Cabling Slowing Plant Go-Live

Completed upfront kVA/BTU power calculations with APC sizing and certified every copper/fibre drop during phased site inspections.

Blind Spots in Manufacturing Site Cybersecurity Posture

Embedded Barracuda security appliances and SIEM log ingestion directly into the campus go-live criteria rather than deferring post-launch.

05 · RESPONSIBILITY, DELIVERABLES & SPECS

Clear split between Brocent and client IT

BROCENT & BROCENT GROUP AFFILIATES HANDLE

  • Full IT architecture design (HLD & LLD), wireless simulation & APC power estimation
  • Structured cabling & 5-vendor build (Aruba, Cisco, Barracuda, APC, HPE) across SH, BJ, GZ (via BROCENT Group affiliates) & HK
  • Cybersecurity hardening, SIEM log pipeline implementation & hybrid cloud integration
  • PMO coordination across the 14-month build and ongoing multi-year maintenance

CLIENT GERMANY HQ & APAC IT RETAIN

  • Global manufacturing IT standards, HLD/LLD sign-off & SIEM correlation rules
  • Facility construction readiness, electrical mains supply & HVAC infrastructure
  • Ownership of OEM hardware assets, software licences & hybrid cloud subscriptions
  • Site commissioning acceptance and ongoing operational SLA governance

DOCUMENTS & AUDIT RECORDS HANDED OVER

German-HQ-Approved High-Level & Low-Level Design (HLD/LLD) Binders
APC Power/Thermal Sizing & Campus Wireless Simulation Reports
Certified Structured Cabling Test Results & As-Built Rack Diagrams
5-Vendor (Aruba, Cisco, Barracuda, APC, HPE) Commissioning & UAT Packs
Cybersecurity Policy Baseline, SIEM Ingestion Proof & Hybrid Cloud Docs
Four-Site Ongoing Maintenance Runbook & Asset Lifecycle Register

ENVIRONMENT & CONTRACT SUMMARY

Location / Facility
Shanghai, Beijing, Guangzhou & Hong Kong (HQ: Germany)
Scenario
Campus Data Centres, Multi-Vendor Build & SIEM
Timeframe
Feb 2019 – Apr 2022 (14 months build + ongoing)
Delivery Model
German HQ engineering alignment + Mainland China campus builds via BROCENT Group affiliates
Contracting Entity
Brocent Hong Kong / Singapore HQ (HKD / SGD / USD; Mainland China delivered locally via BROCENT Group affiliates)

06 · MEASURED RESULTS & OUTCOMES

Before vs. after operational impact

Multi-Site Architecture Consistency
Before Divergent local factory server rooms lacking HQ standards
After Unified HLD/LLD campus data centres across Shanghai, Beijing, Guangzhou & HK
Multi-Vendor Integration Risk
Before Five OEM vendors (Aruba, Cisco, Barracuda, APC, HPE) unmanaged in silos
After Single PMO delivering integrated physical, compute, network & power sign-off
Security & Hybrid Cloud Visibility
Before Isolated plant telemetry invisible to German headquarters
After Centralised SIEM logging, Barracuda perimeter hardening & hybrid cloud sync

“Building four campus data centres across China and Hong Kong to German headquarters standards with five OEM stacks and SIEM integration required disciplined engineering—Brocent delivered the 14-month build and ongoing operations with complete transparency.”

— Head of APAC Infrastructure · Germany-Based Industrial Manufacturer

INCLUDED IN SCOPE

HLD & LLD IT Architecture Aruba / Cisco / Barracuda / APC / HPE Structured Cabling & Power Sizing Campus Wireless Simulation Cybersecurity & SIEM Deployment Hybrid Cloud & Ongoing Maintenance

PLANNING A SIMILAR PROJECT?

Turnkey Campus Data Centre Design, Multi-Vendor Build & SIEM · China & HK

Share your target cities, headcount, and timeline for a scoped SLA and transparent rate card.

EXECUTIVE BRIEF · 2-PAGE A4 PDF

Unlock the 2-page Executive Brief PDF

Read the complete interactive case study on this page, or enter your business details below to immediately unlock the formatted 2-page A4 PDF for offline boardroom sharing.

07 · FREQUENTLY ASKED QUESTIONS

Key technical & commercial questions before starting

How did Brocent align China campus construction with headquarters engineers in Germany?

We produced detailed English HLD/LLD architectures, APC power calculations, and wireless simulations for German HQ approval prior to execution, followed by weekly bilingual PMO tracking across Shanghai, Beijing, Guangzhou (via BROCENT Group affiliates), and Hong Kong.

Which five hardware and security vendors were integrated into the campus data centres?

The four-site build integrated Aruba (wireless/access), Cisco (networking), Barracuda (security), APC (racks/UPS power), and HPE (servers and storage) alongside SIEM and hybrid cloud connectivity.

Does Brocent handle both physical structured cabling and cybersecurity/SIEM?

Yes. Combining physical-layer structured cabling and power sizing with network, compute, Barracuda security, SIEM onboarding, and hybrid cloud integration eliminates handoff gaps between facilities and IT.

What happened after the 14-month campus data centre build completed?

Brocent transitioned all four sites seamlessly into ongoing maintenance through April 2022 and beyond, preserving full engineering continuity from build into steady-state operations.