Global Textile Certification Organisation — DELL R750 / EMC ME5024 / VMware Lab Build, Migration & 37-Server ITAD Across Shanghai & Hong Kong
Client Case Testing, Inspection & Certification · Textiles DELL/EMC/VMware Lab Infrastructure & ITAD

Global Textile Certification Organisation — DELL R750 / EMC ME5024 / VMware Lab Build, Migration & 37-Server ITAD Across Shanghai & Hong Kong

Post-acquisition lab IT infrastructure modernisation across Shanghai and Hong Kong—deploying DELL R750 servers, EMC ME5024 storage, VMware virtualisation, Cisco networking, and Palo Alto firewalls, migrating data and EUC estates, and decommissioning 37 legacy HP servers with certified ITAD data destruction.

37

Legacy HP Servers Retired

2 Sites

Shanghai & Hong Kong Labs

VMware

DELL R750 + EMC ME5024

100%

Certified ITAD Destruction

EXECUTIVE PROJECT SUMMARY

As part of a business acquisition expansion from February 2021 through April 2023, a world-leading textile and apparel certification organisation engaged Brocent to design and implement complete laboratory IT infrastructure across Shanghai and Hong Kong. With Brocent Hong Kong governing programme architecture and Hong Kong site delivery—and BROCENT Group affiliate entities executing Shanghai lab construction, migration, and asset removal—the engagement deployed DELL R750 servers, EMC ME5024 storage, VMware virtualisation, Cisco switching, and Palo Alto firewalls, migrated production data and EUC users, and retired 37 legacy HP servers with certified ITAD data destruction.

Testing, Inspection & Certification · Textiles Shanghai & Hong Kong DELL/EMC/VMware Lab Infrastructure & ITAD Feb 2021 – Apr 2023
L.J. Yu — Senior vCIO · Infrastructure & Wireless
Technically Reviewed By · L.J. Yu

Senior vCIO · Infrastructure & Wireless

Equinix IBX Data Centres · Structured Cabling · Ekahau Wireless Architecture

View vCIO profile →

LAB INFRASTRUCTURE MODERNISATION & CERTIFIED ITAD MATRIX

End-to-end compute, network, migration, and disposal gates across Shanghai and Hong Kong

Compute, Storage & VMware

Target / Legacy Scope: DELL PowerEdge R750 + EMC ME5024 + VMware virtualisation
Execution Standard: Redundant HA cluster, multipath storage & burn-in validation
Audit Evidence: VMware cluster design pack, SAN multipath & health logs

Network & Perimeter Security

Target / Legacy Scope: Cisco campus/lab switching + Palo Alto NGFW firewalls
Execution Standard: Lab-instrument VLAN isolation & strict perimeter rulesets
Audit Evidence: As-built network diagrams & Palo Alto policy baseline

Data & EUC Migration

Target / Legacy Scope: Production lab databases, file shares & acquired EUC fleet
Execution Standard: Phased weekend cutovers with pre/post checksum verification
Audit Evidence: Signed migration UAT & EUC cutover completion register

Decommission & Certified ITAD

Target / Legacy Scope: 37 legacy HP physical servers across Shanghai & Hong Kong
Execution Standard: Serial-verified unrack, chain-of-custody & certified erasure/destruction
Audit Evidence: Serialised Certificates of Data Destruction & ITAD manifest

IT MANAGER EVALUATION & AUDIT BENCHMARKS

Accredited Certification-Lab Modernisation & Chain-of-Custody ITAD Controls

VMware HA · Palo Alto Segmentation · Certified ITAD Chain of Custody

MASSIVE PHYSICAL CONSOLIDATION

37 Legacy HP Servers Consolidated Onto DELL R750 + EMC ME5024

Retiring 37 ageing physical hosts slashed rack power, cooling strain, and hardware failure risk while unlocking VMware snapshot and high-availability capabilities.

LAB-SAFE MIGRATION DISCIPLINE

Zero Disruption to Accredited Testing Operations

Phased weekend migrations validated LIMS applications, instrument interfaces, and EUC logins before legacy systems were retired.

HARDENED POST-M&A PERIMETER

Cisco Switching + Palo Alto Firewalls Standardised

Brought newly acquired Shanghai and Hong Kong laboratory networks under one clean VLAN segmentation and firewall security policy.

AUDITABLE END-OF-LIFE CLOSURE

Certified Data Destruction on All 37 Retired Servers

Client brand test results cannot risk exposure on discarded drives; serial-tracked ITAD certificates closed compliance risk cleanly in both jurisdictions.

IT Manager Field Note: Acquired testing laboratories almost always carry dozens of legacy physical servers holding sensitive client compliance records. Treating new-platform build (DELL/EMC/VMware), data/EUC migration, and certified ITAD disposal as one continuous programme ensures nothing is left half-migrated or uncertified in a storage closet.

01 · PROJECT CONTEXT & CHALLENGES

What the client started with and needed to achieve

LAB EXPANSION FOOTPRINT

Shanghai & Hong Kong · Post-Acquisition Lab Consolidation

Accredited textile and apparel testing laboratories operating LIMS systems, analytical instruments, and confidential brand test records across two Greater China hubs.

DELIVERY & GOVERNANCE MODEL

Brocent HK + Shanghai Onsite via BROCENT Group Affiliates

Single two-year modernisation programme (Feb 2021 – Apr 2023) combining Hong Kong delivery with BROCENT Group affiliate engineering and certified ITAD logistics in Shanghai.

TECHNICAL & COMPLIANCE MANDATE

DELL/EMC/VMware · Cisco/Palo Alto · 37-Server Certified ITAD

Consolidate 37 legacy HP servers onto a modern VMware/DELL/EMC stack behind Palo Alto firewalls while guaranteeing zero data leakage during legacy server disposal.

KEY CHALLENGES & TRIGGERS

  • Replacing 37 ageing physical HP servers across acquired textile testing laboratories in Shanghai and Hong Kong without interrupting accredited lab reporting or client sample testing
  • Designing and commissioning a consolidated DELL R750, EMC ME5024, VMware, Cisco, and Palo Alto architecture spanning both Hong Kong and Mainland China regulatory boundaries
  • Executing audited data migration, EUC migration, physical server decommissioning, and certified ITAD data destruction under strict international certification-body confidentiality rules

02 · DELIVERY WORKFLOW & ARCHITECTURE

Layered reference topology — select any zone or stage

DELL/EMC/VMware Lab Infrastructure & ITAD CN · HK
Active / Primary Path Verified Rollback / HA
ZONE 01 · EDGE & INGRESS 01 DELL R750 · EMC ME5024… DELL R750, EMC ME5024 & VMware Virtualisation Core VMware Shanghai & Hong Kong Primary Path Active · Audited Rollback Gate Pre-tested HA ZONE 02 · CORE & CONTROL PLANE 02 Cisco Network · Palo Alto… Cisco Lab Switching & Palo Alto Firewall Segmentation DELL R750 & EMC ME5024 Build 03 Data Migration · EUC… Zero-Loss Data Migration & Regional EUC Cutover VMware Virtualisation Platform ZONE 03 · PRODUCTION & DELIVERY 04 37 HP Servers… 37-Server Decommission & Certified ITAD Disposal Cisco Network & Palo Alto FW Verified Outcome 37 Legacy HP Servers Retired 2 Sites Shanghai & Hong Kong Labs 24×7 ITIL NOC · ISO/IEC 27001 GOVERNANCE & AUDIT TELEMETRY VMware HA · Palo Alto Segmentation
Layered reference topology — unified typography, active/standby routing & 24×7 governance plane Click any node above or tab below to inspect engineering details
01 DELL R750, EMC ME5024 & VMware Virtualisation Core · DELL R750 · EMC ME5024 · VMware

Engineered and deployed modern DELL PowerEdge R750 hosts paired with EMC PowerVault ME5024 shared storage running VMware virtualisation in both Shanghai (via BROCENT Group affiliates) and Hong Kong, replacing sprawling physical workloads with resilient HA clusters.

FIELD EXECUTION SNAPSHOTS

Three-stage visual delivery walkthrough

01 / 03
DELL R750, EMC ME5024, VMware, Cisco & Palo Alto commissioning
PHASE 1

DELL R750, EMC ME5024, VMware, Cisco & Palo Alto commissioning

Built redundant DELL PowerEdge R750 compute clusters, EMC PowerVault ME5024 shared storage, VMware virtualisation, Cisco switching, and Palo Alto firewalls across Shanghai (via BROCENT Group affiliates) and Hong Kong.

03 · IMPLEMENTATION NARRATIVE

How our engineers executed and verified this engagement

01

Post-Acquisition Lab Discovery & Target Architecture (Feb–May 2021)

Brocent audited acquired laboratory server rooms in Shanghai (via BROCENT Group affiliates) and Hong Kong, cataloguing 37 legacy HP servers, lab software dependencies, and network bottlenecks to finalise the DELL R750, EMC ME5024, VMware, Cisco, and Palo Alto blueprint.

02

DELL/EMC/VMware Cluster & Cisco/Palo Alto Network Deployment

Engineers installed and commissioned DELL R750 compute hosts, EMC ME5024 storage arrays, VMware virtualisation clusters, Cisco switches, and Palo Alto firewalls across both sites—validating failover and backup paths before workload cutover.

03

Phased Lab Data Migration & Regional EUC Cutover (2022)

Production laboratory data, virtualised workloads, and EUC workstations were migrated in controlled weekend waves with full checksum and application UAT verification, keeping certification throughput uninterrupted.

04

37-Server Decommissioning & Certified ITAD Closure (Q1–Apr 2023)

Once all workloads ran stably on the new VMware clusters, Brocent and BROCENT Group Shanghai affiliates unracked all 37 legacy HP servers and executed certified ITAD data destruction, closing the programme in April 2023 with full serialised certificates.

04 · PRACTICAL RISKS & MITIGATION

4 issues that typically go wrong—and how we prevented them

Laboratory Accreditation Disruption During Legacy HP Server Migration

Built parallel DELL R750 / EMC ME5024 VMware clusters first and ran staged weekend migrations with rollback checkpoints.

Instrument-to-Server Connectivity Failure Under New Firewall Rules

Mapped legacy lab-device traffic flows in advance and staged Palo Alto policies in monitor mode before enforcing VLAN segmentation.

Confidential Certification Data Exposure on 37 Retired HP Servers

Enforced serial-level drive tracking, sealed chain-of-custody removal, and certified ITAD data destruction in both Shanghai and Hong Kong.

Schedule Drift Across Two Jurisdictions Over a Two-Year M&A Rollout

Governed Shanghai (via BROCENT Group affiliates) and Hong Kong under one Brocent PMO with milestone UAT sign-offs from Feb 2021 to Apr 2023.

05 · RESPONSIBILITY, DELIVERABLES & SPECS

Clear split between Brocent and client IT

BROCENT HK & BROCENT GROUP AFFILIATES HANDLE

  • DELL R750 server, EMC ME5024 storage & VMware virtualisation design and build (Shanghai via BROCENT Group affiliates)
  • Cisco network switching & Palo Alto firewall configuration across Shanghai and Hong Kong
  • Phased lab data migration, EUC migration & weekend cutover verification
  • Physical decommission of 37 legacy HP servers & certified ITAD data destruction

CLIENT GLOBAL IT & LAB OPERATIONS RETAIN

  • Lab software (LIMS) application testing sign-off & certification compliance rules
  • Approval of weekend migration windows & Palo Alto firewall security policies
  • Ownership of DELL/EMC/Cisco/Palo Alto hardware assets & VMware licences
  • Final acceptance of migration UAT and ITAD destruction certificates

DOCUMENTS & AUDIT RECORDS HANDED OVER

Shanghai & Hong Kong DELL R750 / EMC ME5024 / VMware As-Built Architecture Pack
Cisco Network Topology & Palo Alto Firewall Security Policy Documentation
Phased Data Migration & EUC Cutover Runbooks with Signed UAT Logs
37-Server Legacy HP Decommissioning & Rack-Clearance Sign-Off Sheet
Serialised Chain-of-Custody Manifest & Certified ITAD Data Destruction Certificates
Operational Handover & Post-Build Maintenance Guide

ENVIRONMENT & CONTRACT SUMMARY

Location / Facility
Shanghai & Hong Kong
Scenario
DELL/EMC/VMware Lab Infrastructure & ITAD
Timeframe
Feb 2021 – Apr 2023
Delivery Model
Brocent HK engineering + Shanghai lab delivery via BROCENT Group affiliates
Contracting Entity
Brocent Hong Kong / Singapore HQ (HKD / SGD / USD; Mainland China delivered locally via BROCENT Group affiliates)

06 · MEASURED RESULTS & OUTCOMES

Before vs. after operational impact

Server Footprint & Resilience
Before 37 ageing physical HP servers with high failure & power overhead
After Consolidated DELL R750 + EMC ME5024 VMware HA virtualisation
Network & Perimeter Security
Before Legacy acquired-lab switches lacking unified firewall segmentation
After Standardised Cisco network core & Palo Alto next-gen firewalls
Decommission & Audit Closure
Before Sensitive certification data stranded on 37 retired HP drives
After 100% serial-reconciled ITAD with certified data destruction

“Consolidating 37 ageing HP servers across our acquired Shanghai and Hong Kong laboratories onto DELL R750, EMC ME5024, and VMware—and closing out with certified ITAD destruction—gave us a clean, secure lab foundation with zero testing downtime.”

— Regional IT Infrastructure Manager · Global Textile Certification Organisation

INCLUDED IN SCOPE

DELL R750 & EMC ME5024 Build VMware Virtualisation Platform Cisco Network & Palo Alto FW Lab Data & EUC Migration 37 Legacy HP Servers Retired Certified ITAD Data Destruction

PLANNING A SIMILAR PROJECT?

Lab Server/Storage Build, VMware Migration & Certified ITAD · CN & HK

Share your target cities, headcount, and timeline for a scoped SLA and transparent rate card.

EXECUTIVE BRIEF · 2-PAGE A4 PDF

Unlock the 2-page Executive Brief PDF

Read the complete interactive case study on this page, or enter your business details below to immediately unlock the formatted 2-page A4 PDF for offline boardroom sharing.

07 · FREQUENTLY ASKED QUESTIONS

Key technical & commercial questions before starting

What hardware and virtualisation stack replaced the 37 legacy HP servers?

Brocent deployed DELL PowerEdge R750 servers, EMC PowerVault ME5024 shared storage, VMware virtualisation clusters, Cisco switches, and Palo Alto firewalls across both Shanghai and Hong Kong.

How did you deliver Shanghai onsite work alongside Hong Kong?

Brocent Hong Kong led overall governance and Hong Kong delivery, while Shanghai laboratory installation, migration, decommissioning, and ITAD logistics were executed locally via BROCENT Group affiliate entities.

How was data security guaranteed when retiring the 37 legacy HP servers?

Every retired server and drive was serial-tracked from unrack through certified ITAD data destruction, issuing formal audit certificates confirming zero residual data.

Did the migration cover both backend servers and lab EUC users?

Yes. Alongside server and storage data migration onto VMware, Brocent completed regional EUC workstation migration and Palo Alto/Cisco network cutover across both sites.

Related service

Lab Server/Storage Build, VMware Migration & Certified ITAD · CN & HK